RDI

RDI workflow

Pre-Construction Baseline & Site Condition Documentation

the evidence system cameras and 360° capture deployed at project mobilisation to create comprehensive timestamped visual record of site conditions before construction commences.

Category
Progress Tracking & Documentation
Frequency
Common
Confidence
Medium
Evidence records
10
Cost model
Qualitative

Trigger, activity, conclusion

01 · Trigger

Project mobilisation — contractor establishes site compound, prepares to commence works. PM/legal team identifies need to document existing conditions before ground disturbance/demolition/traffic movements.

02 · Activity

Conducting systematic pre-construction condition survey — using 360° for interior/adjacent buildings, fixed cameras for external areas/boundaries, drone for aerial overview.

03 · Conclusion

Baseline condition record complete and archived. Record available for immediate retrieval throughout project and post-completion liability period.

Workflow steps

  1. Step 01

    Prior to site works commencement, PM identifies pre-construction survey scope.

    Inferred
  2. Step 02

    Neighbours/adjacent property owners formally notified; consent obtained where required.

    Inferred
  3. Step 03

    360° capture walkthrough conducted of all interior spaces within site boundary.

    Evidenced
  4. Step 04

    360° capture conducted in adjacent properties and along site perimeter.

    Evidenced
  5. Step 05

    Drone flight commissioned to capture aerial photographs and video of the site.

    Inferred
  6. Step 06

    Fixed the evidence system cameras positioned for ongoing high-risk boundary area monitoring.

    Evidenced
  7. Step 07

    All captured material archived in the evidence system platform with accurate timestamps.

    Inferred
  8. Step 08

    Pre-construction condition report compiled and formally issued to relevant parties.

    Inferred
  9. Step 09

    Archived record maintained throughout project and post-completion liability period.

    Inferred

Evidence records

Before commencing demolition works adjacent to a Victorian terrace, the contractor used the evidence system 360° capture to document the existing condition of party walls, cracked brickwork, and existing settlement in neighbouring properties — "without that record, we'd have no defence against any crack that appeared during piling."
Anonymized evidence record 38.1
The client's legal team required a full pre-construction condition survey as a contract condition. The contractor used 360° capture and fixed cameras to produce a comprehensive baseline record that was formally submitted to the client and archived — referenced eighteen months later when a neighbour claimed that site traffic had damaged their driveway (the pre-construction record showed the damage pre-existed construction).
Anonymized evidence record 38.2

ROI model

Qualitative workflow

This workflow is currently represented as a qualitative benefit. A parametric cost model should be added only when the assumption set is credible.