Pay Application / Progress Claim Visual Verification
cloud recordings and snapshot tools used to cross-reference visual state of works against percentage-complete claimed in subcontractor's monthly pay application.
- Category
- Subcontractor & Labour Management
- Frequency
- Common
- Confidence
- High
- Evidence records
- 10
- Cost model
- Qualitative
Trigger, activity, conclusion
Subcontractor submits monthly pay application asserting percentage of work complete that the main contractor's QS believes may be overstated or inconsistent with recent observations.
Reviewing the evidence system recordings and snapshots from the claim period to establish a visual baseline of work actually completed.
Pay application certified at face value (with visual confirmation), adjusted downward with evidenced justification, or returned for revision.
Workflow steps
- Step 01
Subcontractor submits monthly pay application/interim progress claim.
Inferred - Step 02
QS/PM reviews claim and identifies inconsistencies with site observations.
Inferred - Step 03
QS/PM accesses the evidence system platform and navigates to the relevant date range.
Evidenced - Step 04
Live or recorded footage reviewed across relevant camera angles.
Evidenced - Step 05
Snapshots taken from the evidence system platform to capture work condition at claim date.
Evidenced - Step 06
Where cloud resolution insufficient, higher-resolution local recording exported or 360° reviewed.
Inferred - Step 07
Visual evidence compared against claimed percentages.
Inferred - Step 08
QS prepares revised assessment/certification recommendation.
Evidenced - Step 09
Adjusted certification communicated to subcontractor with footage references available.
Inferred - Step 10
Certified amount approved for payment or disputed with footage record available.
Inferred
Evidence records
Visual verification of claimed work percentages via camera recordings used to support or challenge monthly payment applications — confirming the workflow's direct commercial application.
Cross-referencing site camera evidence against subcontractor valuations to establish whether claimed progress reflects actual site conditions at the time of the claim.
We manage to save €100k in contractor over charges.
ROI model
dispute claims
Evercam provides visual evidence that resolves or prevents disputes with subcontractors, suppliers, and clients. Saving from faster resolution, avoided escalation, and prevented overcharges.
saving = (disputes_avoided_pct × disputes_per_year × avg_resolution_cost) + (overcharges_prevented_per_year × avg_overcharge_value)