Pay Application / Progress Claim Visual Verification

cloud recordings and snapshot tools used to cross-reference visual state of works against percentage-complete claimed in subcontractor's monthly pay application.

Category
Subcontractor & Labour Management
Frequency
Common
Confidence
High
Evidence records
10
Cost model
Qualitative

Trigger, activity, conclusion

01 · Trigger

Subcontractor submits monthly pay application asserting percentage of work complete that the main contractor's QS believes may be overstated or inconsistent with recent observations.

02 · Activity

Reviewing the evidence system recordings and snapshots from the claim period to establish a visual baseline of work actually completed.

03 · Conclusion

Pay application certified at face value (with visual confirmation), adjusted downward with evidenced justification, or returned for revision.

Workflow steps

  1. Step 01

    Subcontractor submits monthly pay application/interim progress claim.

    Inferred
  2. Step 02

    QS/PM reviews claim and identifies inconsistencies with site observations.

    Inferred
  3. Step 03

    QS/PM accesses the evidence system platform and navigates to the relevant date range.

    Evidenced
  4. Step 04

    Live or recorded footage reviewed across relevant camera angles.

    Evidenced
  5. Step 05

    Snapshots taken from the evidence system platform to capture work condition at claim date.

    Evidenced
  6. Step 06

    Where cloud resolution insufficient, higher-resolution local recording exported or 360° reviewed.

    Inferred
  7. Step 07

    Visual evidence compared against claimed percentages.

    Inferred
  8. Step 08

    QS prepares revised assessment/certification recommendation.

    Evidenced
  9. Step 09

    Adjusted certification communicated to subcontractor with footage references available.

    Inferred
  10. Step 10

    Certified amount approved for payment or disputed with footage record available.

    Inferred

Evidence records

Visual verification of claimed work percentages via camera recordings used to support or challenge monthly payment applications — confirming the workflow's direct commercial application.
Anonymized evidence record 41-alt.1
Cross-referencing site camera evidence against subcontractor valuations to establish whether claimed progress reflects actual site conditions at the time of the claim.
Anonymized evidence record 41-alt.2
We manage to save €100k in contractor over charges.
Anonymized evidence record 41-alt.3

ROI model

Template E

dispute claims

Evercam provides visual evidence that resolves or prevents disputes with subcontractors, suppliers, and clients. Saving from faster resolution, avoided escalation, and prevented overcharges.

Formula

saving = (disputes_avoided_pct × disputes_per_year × avg_resolution_cost) + (overcharges_prevented_per_year × avg_overcharge_value)