RDI workflow
Concrete Pour & Structural Work Documentation
the evidence system fixed cameras and 360° capture document concrete pours and structural installations in real time — recording timestamps, equipment, personnel, pre-pour formwork/rebar condition, and post-pour curing.
- Category
- Progress Tracking & Documentation
- Frequency
- Common
- Confidence
- High
- Evidence records
- 15
- Cost model
- Qualitative
Trigger, activity, conclusion
Concrete pour or major structural installation scheduled — requiring contemporaneous documentation for programme verification, QA, and precautionary record against future defect allegations.
Capturing continuous timestamped visual record — pre-pour inspection through pouring to post-pour curing and formwork stripping.
Pour/structural installation documented with complete timestamped video record retained in the evidence system archive.
Workflow steps
- Step 01
Concrete pour/structural installation scheduled; method statement/mix design finalised.
Inferred - Step 02
Pre-pour inspection conducted by site engineer.
Inferred - Step 03
the evidence system camera coverage confirmed for pour location; 360° capture set up if needed.
Evidenced - Step 04
Concrete delivery vehicles arrive; Gate Report ANPR records arrival/departure times.
Evidenced - Step 05
Pour commences; the evidence system records continuous operation with timestamps.
Evidenced - Step 06
Any visible deviations from method statement observable in footage as NCRs.
Inferred - Step 07
Pour completed; footage records completion timestamp, post-pour finishing, curing.
Evidenced - Step 08
Concrete test cubes taken; references and timestamps noted in pour register.
Inferred - Step 09
Formwork stripping and post-cure inspection documented.
Inferred - Step 10
All records consolidated in structural QA file and retained for statutory period.
Inferred
Evidence records
preserved footage used to verify the exact start and end times of a concrete pour — confirming that the pour was completed within the specified time window, validating the subcontractor's invoice for the pour operation and establishing the pour duration for QA records.
Footage retrieved following a structural concern about a concrete element — providing a timestamped visual record of the pour conditions, the rebar arrangement visible before pouring, and the delivery sequence, contributing to the engineer's root cause investigation.
Gate Report vehicle records used to cross-check concrete truck arrival times against delivery dockets — illustrating the multi-tool documentation approach applied to structural pour verification.
ROI model
dispute claims
Evercam provides visual evidence that resolves or prevents disputes with subcontractors, suppliers, and clients. Saving from faster resolution, avoided escalation, and prevented overcharges.
saving = (disputes_avoided_pct × disputes_per_year × avg_resolution_cost) + (overcharges_prevented_per_year × avg_overcharge_value)